Building process of the business center GEOLOG 2

Active construction of a business center under the Blank project is underway on Obrucheva Street in Moscow. The building GEOLOG 2 is being erected by the developer Hutton Development.

Today, the floor slab of the 2nd floor has already been poured on the site. 30% of the floor slab -1 floor is concreted: preparation for reinforcement and concreting of the part of the floor slab 1 floor is underway. In the underground part they are preparing for masonry works.

The project GEOLOG 2 will be located in an active business district behind the TTC. In its architectural concept we supported the idea of “tectonic shifts” realized in the first phase of the project, but chose a contrasting facade solution to give the building individuality.